LAND Remediation, Inc. (LRI) is currently executing a three-year remediation project at a former chemical facility impacted by an estimated 470,000 lbs of chlorinated solvents, dominated by tetrachloroethene (PCE). The site contains 149,000 cubic yards of impacted soil across a 2.2-acre footprint, with contamination extending to depths exceeding 50 feet below ground surface.
In place of traditional excavation and off-site disposal methods, LRI and our teaming partners constructed the largest known In-Situ Thermal Remediation (ISTR) for Chlorinated Volatile Organic Compounds (CVOC) in 2025. Utilizing heating technology known as Thermal Conductive Heating, 450 thermal heater wells were installed across the treatment zone to remediate the site. This allows contaminants such as PCE to volatilize from the subsurface and be captured by horizontal extraction wells placed under the engineered surface cover and are treated directly on-site.
As of 2026, the ISTR system is now fully constructed and operational, actively removing subsurface contamination. This marks the transition from system construction into full-scale remediation with targeted completion by the end of 2026.
With the site being situated within a designated economic development corridor, the site is slated to be returned to productive use, creating opportunities for future community and economic growth and revitalization.